Plainfield-Naperville Rd (CH 14) from 95th St to 111th St
Roadway reconstruction and widening to two lanes in each direction with landscaped median
|
Naperville
9/07
11/08
$10.7
|
IMPACT ON TRAVEL: Staged construction. Temporary lanes with one lane open in each direction. Occasional temporary lane closures with flagmen. |
|
Arsenal Rd (CH 17) East & West of BNSF Railroad
Roadway reconstruction and widening to five lanes
Signalize I-55 interchange ramps |
Channahon/Elwood
5/06
11/07
$10.0
|
IMPACT ON TRAVEL: Staged construction. Temporary lanes with one lane open in each direction. Occasional temporary lane closures with flagmen. |
|
Manhattan-Arsenal Rd (CH 17) west of IL 53 over Jackson Creek
Bridge replacement
|
Elwood
8/07
11/07
$1.524
|
IMPACT ON TRAVEL: Road closed. Detour directing traffic installed. Also refer to IDOT construction report at http://www.dot.state.il.us/road/will.htm |
|
143rd St (CH 37) at Golden Oak Drive
Intersection turn lanes and traffic signal |
Homer Glen
9/07
11/07
$Letting 8/1/07
|
IMPACT ON TRAVEL: Staged construction. Temporary lanes with one lane open in each direction. Occasional temporary lane closures with flagmen. |
|
Gougar Rd (CH 52) at Laraway Rd (CH 74)
Intersection turn lanes and traffic signal |
New Lenox
7/07
10/07
$0.63 |
IMPACT ON TRAVEL: Staged construction. Temporary lanes with one lane open in each direction. Occasional temporary lane closures with flagmen. |
|
Black Rd (CH 56) at Bronk Rd
Intersection turn lanes and traffic signal |
Shorewood
9/07
11/07
$Letting 8/1/07 |
IMPACT ON TRAVEL: Staged construction. Temporary lanes with one lane open in each direction. Occasional temporary lane closures with flagmen. |
|
143rd St/Gin Mill Rd (CH 76)
from US Route 30 to IL Route 59
Roadway reconstruction and widening to three lanes |
Plainfield
6/06
8/07
$5.8
|
IMPACT ON TRAVEL: Staged construction. Temporary lanes with one lane open in each direction. Occasional temporary lane closures with flagmen. |