  Highway Construction  

Will County Highway Construction - Printable Adobe PDF version.
Print the chart using the Adobe print command not the browser print command.

Plainfield-Naperville Rd (CH 14) from 95th St to 111th St

Roadway reconstruction and  widening to two lanes in each direction with landscaped median

 

Naperville

9/07

11/08

$10.7

 

IMPACT ON TRAVEL: Staged construction. Temporary lanes with one lane open in each direction. Occasional temporary lane closures with flagmen.

Arsenal Rd (CH 17) East & West of BNSF Railroad

Roadway reconstruction and  widening to five lanes

Signalize I-55 interchange ramps

Channahon/Elwood

5/06

11/07

$10.0

 

IMPACT ON TRAVEL: Staged construction. Temporary lanes with one lane open in each direction. Occasional temporary lane closures with flagmen.

Manhattan-Arsenal Rd (CH 17) west of IL 53 over Jackson Creek

Bridge replacement

 

Elwood

8/07

11/07

$1.524

 

IMPACT ON TRAVEL: Road closed. Detour directing traffic installed.

Also refer to IDOT construction report at http://www.dot.state.il.us/road/will.htm

143rd St (CH 37) at Golden Oak Drive

Intersection turn lanes and traffic signal

Homer Glen

9/07

11/07

$Letting 8/1/07

 

IMPACT ON TRAVEL: Staged construction. Temporary lanes with one lane open in each direction. Occasional temporary lane closures with flagmen.

Gougar Rd (CH 52) at Laraway Rd (CH 74)

Intersection turn lanes and traffic signal

New Lenox

7/07

10/07

$0.63

IMPACT ON TRAVEL: Staged construction. Temporary lanes with one lane open in each direction. Occasional temporary lane closures with flagmen.

Black Rd (CH 56) at Bronk Rd

Intersection turn lanes and traffic signal

Shorewood

9/07

11/07

$Letting 8/1/07

IMPACT ON TRAVEL: Staged construction. Temporary lanes with one lane open in each direction. Occasional temporary lane closures with flagmen.

143rd St/Gin Mill Rd (CH 76)

from US Route 30 to IL Route 59

Roadway reconstruction and widening to three lanes

Plainfield

6/06

8/07

$5.8

IMPACT ON TRAVEL: Staged construction. Temporary lanes with one lane open in each direction. Occasional temporary lane closures with flagmen.